Notes on maintenance-free brick machine control system

2014-03-18


As we all know, no matter what the machinery, to prolonged use, maintenance is an essential part of it. Especially in winter, low temperatures, maintenance is especially important. Following are some recommended small clay brick making machine maintenance in winter, hope to be helpful.
1. the brick machine equipment in order to correctly use and maintenance operation, maintenance personnel must have a detailed understanding of the performance and features, not to do it, so as not to hurt people, damaged parts.
2. in examining access to, you should cut off the main power supply, Hung warned.
3. promptly clean up after each class.
4. when all the parts in place, fully automatic cycle operation.
5. the moving parts of the equipment, non-staff at work do not close.
6. operators of non-computer-controlled Cabinet are not free to press the push button to avoid wounding losses.
7. after each shift, electric switch should be in the "off" or "stop" position.
8. the use of thisautomatic fly ash brick making machine must be grounded, as a precautionary measure.
9. cement storage hopper to exhaustion in a timely manner, preventing coagulation.
10. hard aggregate selection to adapt to the mode box side holes, hard foreign body cannot be mixed with material, prevent damage to brick brick mold.
11. the brick machine pallets on solidification of concrete to be cleared in a timely manner.
12. at the end of if not enough, head pressing the bottom to prevent damage to pressure oil cylinder and head structure, resulting in pressure head out of sync.
13. vibration moulding rigorously controlled, forming long, head down, then adjust the amount of cloth.
14. always check limit switch brick machine equipment is in place, if we loose the timely adjustment, tighten limit switch ends with the induction distance is 5-8mm, in case of crash.
15. hydraulic station on the summer, be sure to use the condenser, or oil heating, affecting the normal use, timely oil supplement and replacement, oil filter should be under the flood's directions to replace the filter cartridge, or hydraulic system failure will result.
16. to replace the rubber scrapers on the hopper, and adjusted the gap, otherwise leakage, head-stick material.
17. is required prior to use to tighten all bolts.
18. the vibrating platforms, pallet feeder planes, send brick upper surface must be flat, otherwise the brick machine pallets not smooth transmission, can't push block or cracking.
19. the class work is required prior to lubrication the lubrication in all. Feeder transport belts every cycle to small hopper feed bins below the material should not be too much, nor too little to ensurefree brick equipment little hopper feed bins full-free material as well.
Scattering material due to excessive discharge, too little mould box cloth is not enough.

SKYPE: kevinlee02
QQ: 81573401
Tel: 0086-371-87091886
Fax:0086-371-87091887
E-mail:zzbona@zzbona.com

Name:
*
E-mail:
Message:

Copyright @ Bona enterprise. All rights reserved. Site Index Product Index

Design & Development by sinoart